Construction Summary Report 1/8/18

Construction Summary Report 1/8/18
Posted on //
CGMS/Saguaro construction site"What’s New?
McCarthy is ready to welcome in the new year! The project team is working full steam ahead as we prepare for an exciting 2018/2019 school year! Steel has started at the 2nd -5th Grade Building and Middle School Building which will then kick off roofing. The Administration Building and K-1 st Grade Building are going up with the masonry walls. Lastly, the Multipurpose & Cafeteria Building concrete slab has been poured in preparation to start masonry walls.

The Past Week
 Masonry walls at the 2nd -5th Grade Building were completed for steel joists to be set.
 Temporary power has been installed to provide power for construction throughout the site.
 Utilities are being trenched through the middle of the site to provide sanitary services to each building.

Coming Up in the Weeks Ahead
 The 2nd -5th Grade Building interior walls will be framed to kickoff other trades starting on interior build-out.
 Steel joists will be set in the Admin, K-1 st Grade and Middle School Buildings.
 Masonry is expected to start at the Multipurpose & Cafeteria Building in the coming days.
 HVAC ducts will be hung at the 2nd -5th Grade Building after roofing is complete. "

-McCarthy Building Projects